← All Projects
Electric and Phone Cables Company in the Isolation Gas Station in Majnoon Field

Basra Governorate
Beneficiary
South Oil Company
Commencement Date
5 / 10 / 2001
Completion Date
29 / 12 / 2001
Project Cost
60,245,000 I.D
The project included the execution of drilling and extending telephone and electrical cables, and activating the network, as a whole to ensure its efficiency, and avoiding erosion using 10 CM layer of river sand with, and then embed-ding it in natural soil and leveling it all.